Current lead times
This page is to be used as a quick reference to current component lead times for our most common modifications. For lead times on specific vendors or projects, please reach out to sales@mas-hvac.com
These lead times are based on the lowest lead time vendor option for the listed component.
These lead times are the time it takes for us to receive the component from the time we order.
Last Updated: 10/25/2021
Enthalpy Plates
Q-PAC Arrays
Direct Drive Plenum Fans
Gas Heaters (all types)
Heat Pipes (all types)
Energy Recovery Wheels
Sensible Plates
Electric Heaters
6 - 8 Weeks
16 - 20 Weeks
6 - 8 Weeks
4 - 8 Weeks
6 - 8 Weeks
6 - 8 Weeks
6 - 8 Weeks
4 - 6 Weeks